- Yolanda Torrisi
- +61 412 261 870
- yolanda@yolandatorrisi.com
- Nina van Wyk
- +27 82 926 3882
- nina@africanminingnetwork.com
Shaft 1 at the Platreef project of Ivanhoe Mines in South Africa has reached a depth of 750 metres below surface and lateral development of the first mine access station is underway.
Development of the tier-one PGE, nickel, copper and gold mine on the Northern Limb of South Africa’s Bushveld Complex continues to advance.
The 750-metre station on Shaft 1 will provide initial, underground access to the high-grade ore body, enabling mine development to proceed during construction of Shaft 2, which will become the mine’s main production shaft.
The mining zones in the current Platreef mine plan occur at depths ranging from about 700 metres to 1,200 metres below surface.
Shaft 1’s 750-metre station also will allow access to the first raise-bore shaft that will provide ventilation to the underground workings during the mine’s ramp-up phase.
The first of the mine’s planned fleet of mechanised, mobile, underground mining equipment – a small, 5.5-tonne load-haul-dump machine (LHD) – has arrived on site and will be used for off-shaft station development work on the 750, 850 and 950-metre levels. People from Platreef’s surrounding host communities are being trained as operators of the LHD.
The LHD will be the first piece of mechanised, mobile equipment to be used underground on the northern limb of the Bushveld Complex. The thick, flat-lying ore body at the Platreef project is ideal for bulk-scale, mechanised mining.
As underground development progresses, the mine plan calls for the addition of significantly larger mechanised mining equipment, such as 14 and 17-tonne LHDs and 50-tonne haul trucks.
Sinking of Shaft 1 will resume after the 750-metre station is completed. The shaft is expected to intersect the upper contact of the Flatreef deposit (T1 mineralised zone) at an approximate shaft depth of 783 metres.
As shaft sinking advances, two additional shaft stations will be developed at mine-working depths of 850 metres and 950 metres. Shaft 1 is expected to reach its projected, final depth of 980 metres below surface in 2019.
“Soon we will be able to show our stakeholders and investors Flatreef’s remarkably thick, high-grade mineralised zones that will allow us to be at the forefront of safe, underground bulk mining,” said Ivanhoe's executive chairman Robert Friedland.
“Our focus is to keep advancing the Platreef project along its critical path. Our continued development of shafts 1 and 2 will provide access to the high-grade ore body and help to ensure that the project is able to meet the expected start-up of the first phase of the underground mine and concentrator.”
The Platreef project team and its South African sinking contractor, Aveng Mining, achieved a record monthly shaft-sinking rate of 54 metres in March. The project also has attained 160 days without a lost-time injury, a notable achievement given the safety challenges that shaft-sinking operations encounter.